Process & Costs

Drawings and material samples
Drawings and timber samples on a meeting table
The frame takes shape
A cedar and cypress frame being raised under a blue sky

Around thirteen months from first conversation to handover

Allowing five months for design makes our overall schedule longer than some builders'. Construction itself takes five to six months.

  1. Month 0

    Consultation and brochure request

    Free. We discuss your wishes and budget limit.

  2. Month 1

    Budget and land consultation

    We consider the total, including fees, landscaping, moving and furniture.

  3. Months 2-3

    Site survey and initial plan

    We check the site and present an initial plan and estimate. Everything up to this point is free.

  4. Month 3

    Design application

    A ¥200,000 payment toward the design fee starts detailed design.

  5. Months 4-7

    Detailed design and specifications

    An average of eleven meetings, including showroom visits.

  6. Month 7

    Contract

    We sign against finalized drawings and an estimate.

  7. Month 8

    Building approval and ground survey

  8. Month 8

    Construction begins and ground blessing

    A jichinsai is a traditional Japanese ceremony to bless the site.

  9. Month 9

    Foundations and frame raising

    You can visit the structure after the frame is raised.

  10. Months 10-12

    Interior carpentry and airtightness test

  11. Month 13

    Final inspection and handover

Discussing the floor plan
A meeting with floor plans and timber samples

When payments are due

Design application
¥200,000(Part of the design fee)
Contract
10% of construction cost
Construction starts
30%
Frame raising
30%
Handover
Balance

Home loans are often disbursed in full at handover. Payments at the start of construction and frame raising therefore need bridging finance, a short-term loan until the main mortgage is released, or staged loan disbursements. Your choice of lender needs to consider these options as well as the interest rate. We explain this early in the process.

Drawing a floor plan
Drawing a floor plan with a scale ruler and pencil

We show the total cost first

A price per tsubo, the Japanese floor-area unit of approximately 3.31 m², does not tell you how much you need overall. With our first plan, we show the total in four parts.

Main building work
From ¥680,000 per tsubo (approx. 3.31 m²)Around ¥21,800,000 for 32 tsubo (105.8 m²)
Ancillary work
¥2,500,000-¥4,500,000Ground improvement, water and drainage connections, outdoor electricity and landscaping
Related fees
¥1,800,000-¥2,600,000Design, building approval, registration, fire insurance and loan fees
Other costs
¥800,000-¥2,000,000Curtains, some lighting, furniture, moving and temporary accommodation

Most clients who already own land spend ¥28,000,000-¥36,000,000 in total. Ground improvement requirements are not final until the ground survey, so this allowance may change afterwards.

A single-story home with deep eaves
A single-story home with deep eaves and a deck opening to the garden

When the budget does not fit

An initial proposal can exceed the budget. We have a clear order for adjusting it.

First we review floor area. Removing one tsubo (approximately 3.31 m²) reduces main building costs by about ¥680,000, or around ¥750,000 with ancillary work. Next come the number of rooms and complexity of built-in storage, then equipment grades.

We do not reduce structural performance, insulation, airtightness or waterproofing. Changing these later means opening walls, and doing so in an occupied home is particularly expensive. We explain this order when we first discuss your budget.

Insulation and airtightness
Insulation and an airtight membrane inside a wall

Subsidies and tax relief

Various subsidies and tax relief schemes depend on housing performance, and our standard specifications meet the performance level required by many of them.

Terms, budgets and application deadlines change each year. Your construction schedule may not fit a particular scheme, so we check likely availability when you consult us and handle the preparation and submission of applications.

We ask you not to make your financial plan depend on a subsidy being awarded. The plan should still work without it. Treating a subsidy as money that can go toward an early loan repayment is a safer approach.

Ready for a conversation
Tea and material samples ready for a consultation

Contact & Brochures

First,
we listen.

You may not have chosen land, worked out your budget, or decided whether to rebuild or renovate. These are the questions we hear most often, and this is when we can be most helpful.

Your first consultation is free, and we will not ask you to sign a contract on the spot. Contact us for a conversation, a brochure or a home visit.

First consultation free

Talk to us