Our process

Nine steps from your first inquiry to handover.

  1. 01

    Contact

    Call or use our form. You can carry your choices over from the cost calculator.

  2. 02

    Site survey

    Free of charge. In about an hour, we check the building, road access, distances to neighboring properties and any contents left inside.

  3. 03

    Pre-demolition asbestos survey

    A qualified surveyor reviews drawings and inspects the site, with laboratory testing where needed. Findings are reported as required by law.

  4. 04

    Estimate and contract

    We provide an itemized estimate within two business days of the survey.

  5. 05

    Notifications and neighbor visits

    Demolition of buildings with 80 m² or more of floor area requires notification under Japan’s Construction Material Recycling Act at least seven days before work begins. We prepare the paperwork and visit neighbors with a letter explaining the schedule.

  6. 06

    Screening and hand sorting

    We erect scaffolding and mesh sheeting, then remove and separate interior materials, fixtures, glass and roof tiles by hand.

  7. 07

    Mechanical demolition and foundations

    We suppress dust with water while demolishing the building, then excavate and remove its foundations.

  8. 08

    Sorting and removal

    We separate timber, concrete rubble, scrap metal and plasterboard for removal. Manifests (Japan’s industrial-waste tracking documents) trace the waste to its final disposal site.

  9. 09

    Leveling and handover

    We level the ground and provide a completion report with photographs and documents needed to register the building’s removal from Japan’s property register.

Required notifications

Demolition of buildings with 80 m² or more of floor area requires notification under Japan’s Construction Material Recycling Act at least seven days before work begins. We prepare and submit the documents in your name.

Visiting neighbors

Before work starts, we visit properties on either side and across the road with a letter giving the schedule and contact details.

Pre-demolition asbestos survey

Japanese law requires an asbestos survey before demolition or renovation. A qualified surveyor carries out the survey and reports the findings.

Waste manifests

Manifests are Japan’s industrial-waste tracking documents. They trace business-generated demolition waste through transport to its final treatment and disposal.

Photo reports at every stage

We explain the work sequence when preparing your estimate.