Job summary

LocationFukaya
BuildingDental clinic, 120 m²
The workDisassembly cleaning of 5 four-way ceiling cassette units, update of 1 unit, 3 HP, in the waiting room
Work3 people, on the closed Thursday
Cost¥567,600 (equipment and work)

The request

Water dripped from the waiting room unit, and that led them to ask us to look at everything including the treatment rooms.

A supervisor talking with a dentist in the clinic hallway

The work

We inspected all the units and judged that only the waiting room unit needed updating. Disassembly cleaning was enough for the other 5. We covered the equipment in the treatment rooms before working so the wash water would not reach it.

A technician cleaning a ceiling air conditioner in a waiting room

Afterwards

We finished in time for the next day's appointments. We made an equipment register for all units and moved on to the simple inspection service.

A treatment chair under protective sheets and an open ceiling